RF Testing Independent field verification of RF shielding performance for secure and mission-critical facilities 1-800-665-0080

Selected project experience

Case studies

Acoustic testing, noise investigations, and project assessments.

Explore how On-Site Acoustic Testing has helped clients assess installed performance, locate noise sources, improve products, and make informed decisions in demanding environments.

Client names and identifying locations have been omitted to preserve confidentiality.

01 · Military & Government

Independent verification of approximately 100 acoustic doors

OSAT replaced unreliable test results with a documented verification program. By the end of testing, every door met its required rating; later government testing found one failure on a door with apparent damage.

The challenge

A client at a military installation had been told that its walls and doors were falling well short of their required acoustic ratings. The reported findings included an STC of approximately 30 for a 16-inch-thick solid concrete wall. That result raised questions about how the measurements had been taken.

OSAT was initially brought in to check a few walls and doors. The immediate task was to establish whether the earlier results could be relied upon before the client committed to corrective work.

The testing and corrective work

OSAT reviewed the earlier agency’s approach and found that the testing did not follow the applicable ASTM procedures. The methods were inconsistent, leaving the client without a dependable account of the assemblies’ performance.

The assignment grew to approximately 100 doors. OSAT tested the installed assemblies and worked with the client through adjustments and retesting. The work continued until all of the doors in the program met their required acoustic ratings.

The result

Government personnel subsequently conducted their own testing. Of the approximately 100 doors, only one failed to meet its rating, and that door showed apparent damage.

For the client, the work resolved two problems: uncertainty about the original test results and the need to verify a large number of installed doors. The subsequent government testing provided a separate check on the condition OSAT had documented.

02 · Military & Government

Acoustic door remediation and verification at a military facility

Every door failed the initial testing. Following remediation advice, installer training, and real-time feedback, 100% of the more than 60 doors met their required acoustic rating by the end of testing.

The challenge

OSAT was retained to verify newly installed acoustic doors at a secure facility on a military base. During the initial visit, every door tested failed to achieve the required performance.

Problems with the seals were a major part of the failure. The client needed specific guidance on the installed condition and a way to organize repairs across a substantial number of doors.

The testing and corrective work

OSAT provided advice on seals, caulking, and door fitment, along with installer training. The guidance showed the repair team what to address and how installation details affected the measured result.

OSAT also demonstrated a basic field-screening method the client could use between visits. This helped personnel check their progress during repairs, while formal acceptance remained dependent on OSAT’s verification testing.

The client mobilized an all-hands repair effort. OSAT returned two weeks later and supplied real-time feedback during testing. Some doors passed immediately; others needed further adjustments and another test.

The result

By the end of testing, 100% of the more than 60 doors met their required rating. The project moved from universal failure at the initial visit to verified passing performance for every door in the program.

The result came through installation corrections and repeated measurement. Training and immediate feedback helped installers connect their work to the acoustic requirements and resolve remaining deficiencies.

03 · Military & Government

Acoustic assessment and retesting of existing SCIFs

Testing identified acoustic deficiencies in occupied secure spaces. OSAT returned after remediation to verify that the tested areas met the applicable ICD 705 acoustic requirements.

The challenge

A major U.S. defense contractor retained OSAT to evaluate multiple secure areas within a principal headquarters facility. Some of the SCIFs were believed to date to the 1990s.

The rooms were being used for secure conversations, but their installed sound isolation had not been established by the assessment now required. OSAT’s testing found acoustic deficiencies in several of the areas evaluated.

The assessment

OSAT tested the perimeter of the selected spaces, including doors, floor-to-floor transmission, and demising walls between adjacent areas. The scope examined different parts of the acoustic separation rather than treating door performance as a substitute for the whole perimeter.

OSAT prepared a report documenting the measured performance of the tested areas. It gave the client a record of the existing condition and the deficiencies that required attention.

After remediation was completed, OSAT returned to test the spaces again. The follow-up measurements addressed whether the modifications had achieved the required acoustic performance.

The result

The retested areas met the applicable ICD 705 acoustic requirements. The client had measurements documenting both the original condition and the performance after corrective work.

The assignment demonstrated why existing secure rooms need assessment of their actual construction. The age and continued use of a space did not establish its sound isolation; the testing supplied that information.

04 · Data Centers & Environmental Noise

Independent noise testing and evidence review for a data center

OSAT measured property-boundary noise and reviewed the methods behind excessive-noise allegations. The principal legal action was later withdrawn; a limited ordinance matter remained open.

The challenge

A law firm representing a data center retained OSAT after neighboring property owners alleged excessive noise on adjacent properties. The neighbors had engaged their own counsel, and the dispute also involved local police enforcement of a county noise ordinance.

The law firm needed an independent measurement of the noise and a review of the information being presented as evidence of exceedances.

The measurements and review

OSAT conducted additional testing to determine the noise levels at relevant property boundaries and advise the law firm on their relationship to the applicable limits.

OSAT then examined the opposing measurements and the methods used to obtain them. The review identified concerns with the meter’s suitability, a lack of recent calibration, an inappropriate measurement scale, and inconsistent procedures.

Video footage recorded during the police officer’s testing was available for review. It allowed OSAT to examine the collection process directly and identify errors in how the readings had been obtained.

The result

The law firm received independent measurements and a technical assessment of the evidence supporting the allegations. Those were separate questions: what noise was present, and whether the earlier readings had been collected in a way that supported their stated conclusions.

The principal legal action was subsequently withdrawn. At the time of this account, a limited matter involving the local noise ordinance remained open.

05 · Building Acoustics

Comparing floor-ceiling assemblies for future apartment construction

Testing across several apartment buildings helped a developer select floor-ceiling assemblies and standardize construction methods for future projects.

The challenge

A large apartment developer wanted to know which floor-ceiling constructions performed best before adopting them for future buildings. The choices involved underlayment, insulation, framing or stud type, and finished flooring materials.

The question concerned the assembled construction. Selecting an individual material did not, by itself, answer how a completed floor-ceiling system would perform.

The comparison

OSAT tested multiple samples across several buildings for both airborne and structure-borne sound transmission. The work compared the combinations of materials and construction details the developer was considering.

Measuring both types of transmission allowed the developer to assess the different performance concerns within the same program. The results identified the combinations that performed best under the tested conditions and gave the client a basis for selecting preferred assemblies.

The findings were then used to standardize building methods for new construction. Instead of making each material choice independently, the developer could specify combinations informed by measurements of the assembled systems.

The result

The testing influenced methods intended for use in future apartment buildings. Its value extended beyond the sampled properties because the developer was establishing a repeatable approach to new construction.

OSAT understood from the client’s experience that the approach also helped avoid tenant complaints about sound transmission. Fewer complaints and improved tenant retention were practical goals of the work.

06 · Product Noise & Diagnostics

A rear-grille change reduces handheld blower noise by more than 10 dB

Sound intensity testing traced an objectionable whistle to the blower’s rear grille. A modified grille was adopted in production, reducing overall noise by more than 10 decibels.

The challenge

A leading television direct-to-consumer marketer supplied OSAT with multiple handheld blowers intended for leaf cleanup and household use. The units produced excessive noise, including a high-pitched whistle that made the sound particularly objectionable.

The client wanted to establish the product’s noise output, understand how it compared with competing products, and identify the source of the whistle.

The investigation

OSAT used sound intensity testing to evaluate the supplied units. Competitor products were obtained and tested as part of the comparison.

The investigation identified the rear grille as the source of the high-pitched whistle. This narrowed the problem from a general complaint about a loud product to a particular feature that could be changed.

OSAT modified a sample by replacing the original rear grille with a screen-style grate. The modification addressed the component identified during testing and gave the client a specific alternative to incorporate into the product design.

The result

The grille change was subsequently implemented in production units. The revised design reduced the overall noise level by more than 10 decibels.

The assignment linked measurement to a manufacturing decision. Competitor testing provided context, source investigation identified the component responsible for the objectionable sound, and the sample modification led to a change in the units sold to customers.

07 · Aviation & Speech Intelligibility

Ground and in-flight testing of cabin announcements

A two-hour test flight and ground evaluations informed headset, volume, and gain-staging recommendations that the airline adopted across its fleet of similar aircraft.

The challenge

A regional airline operating services for a major U.S. airline retained OSAT to investigate cabin announcements that were difficult to understand at different flight levels.

The airline made an aircraft available with a pilot, co-pilot, and supporting personnel. This allowed the announcement system to be assessed under the conditions in which the problem occurred.

The testing

OSAT performed speech intelligibility testing using an NTi TalkBox and actual aviation headsets. Several headsets were evaluated, including Bose and David Clark models.

Ground testing included different aircraft systems operating, including HVAC. OSAT then conducted testing during a two-hour flight at multiple flight levels. The combination allowed evaluation of the announcement system beyond a stationary aircraft with its systems switched off.

OSAT assessed headset selection and announcement volume and discussed gain staging to minimize distortion. The recommendations addressed how the equipment and system settings worked together, rather than relying on a volume increase alone.

The result

OSAT identified preferred headset choices and appropriate announcement settings, with guidance on gain staging. The airline subsequently applied the recommendations throughout its fleet of similar aircraft.

The work translated a problem experienced during operation into settings and equipment choices the airline could use consistently. The ground and flight evaluations supplied the operating context for those recommendations.

08 · Source Localization

Locating a piping defect with a parabolic microphone

An acoustic survey located a suspected leak in difficult-to-access piping after other methods had failed to isolate its source. The defect was then repaired.

The challenge

A client suspected a leak in a large section of low-pressure, high-volume piping. Several other methods had already been tried without successfully isolating the location.

Access was a significant part of the problem. The underside and other portions of the installation were normally difficult to reach, and the suspected leak could not be investigated as a readily accessible, localized defect.

The client described a sound associated with loss of pressure. OSAT used that description as the starting point for an acoustic search.

The survey

OSAT developed a plan to scan the piping with a parabolic microphone, including the underside and the normally inaccessible areas.

The purpose was to locate the sound associated with the suspected leak and narrow the search to a repairable defect. The survey approach was selected around the size of the installation and the access limitations that had complicated the earlier attempts.

The investigation used sound to find the source rather than requiring the client to first identify a visible defect along the piping.

The result

OSAT successfully located the defect, which was subsequently repaired.

The completed work provided the client with a specific repair location after previous approaches had left the leak unresolved. This was a source-location assignment: the immediate value was finding where corrective work was needed within a large, difficult-to-access installation.

09 · Building Acoustics & Broadcasting

Sound-isolation testing and door design support for broadcast pods

OSAT verified broadcast pod sound isolation and helped develop a door assembly that performed consistently with the surrounding construction. The pods have been used for national and international broadcasts.

The challenge

A manufacturer of pods used by broadcasters at major sporting events retained OSAT to verify their acoustic performance. The pods were intended for events attracting national and international audiences.

The manufacturer also needed assistance with the door assembly. Its performance needed to match the surrounding construction materials so the opening would not undermine the enclosure’s intended sound isolation.

The testing and design support

OSAT verified the pods’ STC performance and assisted with the door assembly design.

The work considered the door as part of the completed enclosure. The main construction and the opening had to be addressed together when evaluating whether the pod provided the required acoustic separation.

This combined verification with a specific design question. The manufacturer received information about measured performance and assistance with the component that needed attention, rather than an acoustic rating without guidance on the door.

The result

The pods have been used for national and international broadcasts. The manufacturer plans to deploy them at additional major global sporting events.

OSAT’s role was to establish acoustic performance and help align the door assembly with the rest of the construction. The manufacturer could use the findings to address the opening as part of the pod’s overall design.

10 · Hospitality & Environmental Assessment

Noise and lighting assessments at a luxury waterfront hotel

OSAT identified noise affecting speech and guest comfort, along with overlit and underlit public areas. Recommendations addressed guest visibility and the needs of a turtle-nesting beachfront.

The challenge

A luxury waterfront hotel operated by an international hospitality company retained OSAT to assess noise in indoor and outdoor areas and light levels in public walkways and other guest spaces.

The beachfront was also habitat for nesting turtles. The lighting question involved competing needs: suitable visibility for guests and limiting light that could interfere with the turtles’ natural cycles. Simply increasing or reducing lighting throughout the property would not address both objectives.

The surveys

OSAT measured light levels in the relevant public areas and identified locations that were overlit and others that were underlit. These findings gave the hotel information about where lighting needed attention, rather than treating the property as uniformly too bright or too dark.

OSAT also assessed noise throughout indoor and outdoor areas. The survey identified locations where sound levels interfered with speech intelligibility and guest comfort.

The two assessments addressed different aspects of the same property. Walkway visibility, comfortable communication, and the sensitive beachfront setting all formed part of the recommendations delivered to the hotel.

The result

OSAT provided a set of recommendations for a more balanced lighting approach and identified noise conditions requiring attention.

The hotel received a documented basis for planning changes in its public areas, with attention to both the guest experience and the sensitive beachfront setting.

11 · Hospitality & Building Acoustics

Guest-room acoustics at an exclusive private club

Testing and recordings documented neighborhood noise intrusion and transmission from the lounge and musical performance area. Ownership received findings, remediation advice, and recommendations for further investigation.

The challenge

An exclusive private club occupied a converted building with high-end guest suites, a private lounge on the top floor, and a musical performance area. The interior noise conditions did not match the pricing and expectations associated with the guest experience.

The concerns involved several sources and parts of the construction. Neighborhood noise entered through inadequate glazing, while the lounge and performance area transmitted sound to guest rooms.

The assessment

OSAT conducted noise-level measurements and AIIC and ASTC testing. Audio recordings in selected guest rooms also illustrated the typical guest experience, allowing ownership to hear the conditions alongside the numerical results.

The assessment identified glazing that was inadequate for the surrounding noise levels and problems with floor-ceiling sound transmission associated with the lounge’s construction and terrazzo floor.

OSAT also identified direct sound transmission from the musical performance area to multiple guest rooms. Issues with the performance stage’s construction, attachment, and coupling to the building structure were documented, with further investigation recommended.

The findings and remediation advice were provided to ownership. Information concerning the stage and its relationship to the structure was also supplied to the architectural consultants.

The result

Ownership received an organized assessment of the conditions affecting its guest suites, with several areas requiring attention. The work distinguished exterior noise intrusion from transmission associated with the property’s entertainment spaces.

Management’s decisions about remediation remain undetermined. The completed outcome is the documentation and advice delivered to ownership and its consultants; improvements following corrective work have not yet been established.

12 · Residential & Dispute Support

Continuous monitoring of noise from a neighboring commercial property

Several weeks of round-the-clock measurements and audio recordings documented activity beside a homeowner’s backyard. The information was used in a dispute that ended with the business owners purchasing the home above market value.

The challenge

A homeowner retained OSAT after a neighboring property changed ownership. The property had operated as a small store for many years, but the new owners added an outdoor eating area immediately beside the homeowner’s backyard.

The area was intended to operate during very limited hours. According to the homeowner, its use expanded into restaurant and lounge activity, raising concerns about operating hours and the property’s permitted use.

The homeowner needed a record of the activity over time. The dispute concerned recurring operations, so documenting a single short visit would not have captured the full pattern.

The monitoring

OSAT conducted several weeks of 24/7 noise monitoring with audio recording. This produced a record of measured levels together with recordings of the activity occurring during the monitoring period.

The recordings complemented the measurements by documenting the character of the sound. The extended monitoring period also provided information about when the activity occurred and how long it continued.

The information was used to support the homeowner’s position concerning the business’s operating hours and permitted use.

The result

The dispute was ultimately resolved through the store owners’ purchase of the homeowner’s property for significantly above market value.

OSAT’s monitoring supplied documentation used in reaching that resolution. The purchase was the subsequent outcome reported by the client, rather than a financial result determined by the noise measurements themselves.

13 · Pickleball & Residential Planning

Assessing pickleball noise before courts were built

Baseline measurements and modeling using recorded pickleball noise informed landscape and screening decisions for proposed courts near condominium buildings.

The challenge

A large residential condominium development was considering new pickleball courts near existing residential buildings. The area already contained tennis courts and other recreational activities.

The development retained OSAT before construction to assess the likely effect on the nearest buildings. The project team wanted information it could use while the court surroundings and landscape treatment were still being planned.

The measurements and modeling

OSAT measured the existing sound levels at the residential buildings closest to the proposed court location. These measurements established the baseline in an area that already had recreational sound.

OSAT then used actual pickleball noise measurements from earlier monitoring projects, together with the proposed separation distances, to model the projected levels at the nearby buildings.

The assessment combined site-specific baseline measurements with measured pickleball activity. It gave the project team an estimate of the proposed courts’ noise contribution in the context of the existing surroundings.

The information was used with the landscape architects to identify appropriate ground cover and screening intended to reduce disturbance to residents.

The result

The development had noise assessment information available during design, when decisions about the court surroundings could still be made.

The assessment supported decisions about the proposed installation’s ground cover and screening. Post-construction noise measurements have not been reported.

14 · Pickleball & Dispute Support

Documenting pickleball noise beside a home

Noise monitoring and audio recordings documented court operations near a homeowner’s property line, providing information for the homeowner’s attorney.

The challenge

A homeowner retained OSAT after a pickleball court was installed on a neighboring lot within a residential subdivision. The court was approximately three feet from the client’s property line.

The client’s home was a high-end property, but it was not separated from the court by a large acreage. The proximity of play raised concerns about the effect of court operations on the home.

The homeowner needed documentation that could be presented by an attorney. The assignment concerned an existing court and its operating impact, rather than a prediction of noise from a proposed facility.

The monitoring

OSAT conducted noise-level monitoring with audio recording to document the court’s activity and the sound affecting the client’s property.

The measurements supplied numerical information, while the recordings captured the audible character of play. Using both allowed the material presented to the attorney to include more than a description of the homeowner’s concerns.

The work focused on documenting conditions associated with the court’s operation so the homeowner’s position could be supported by a measurement record.

The result

OSAT provided monitoring information for use by the homeowner’s attorney in presenting the effects of the court’s operations.

The outcome described here is the collection and delivery of that evidence. A subsequent legal resolution or verified reduction in noise has not been reported.

15 · Multifamily & Acoustic Due Diligence

Sound isolation testing guides flooring choices across eight apartment communities

AIIC and ASTC testing at eight acquired apartment complexes helped ownership decide where hard-surface flooring could be considered and where carpeting needed to remain.

The challenge

A major U.S. multifamily developer and apartment leasing company retained OSAT after purchasing eight apartment complexes from other owners.

The company needed baseline information about sound isolation before making flooring decisions. Some buildings were candidates for hard-surface flooring, while others needed to remain carpeted to support the acoustic performance ownership sought.

The decision concerned existing buildings with different construction conditions. A single flooring choice across the acquired properties would not have answered whether each building could accommodate that change.

The testing

OSAT measured AIIC and ASTC performance at the eight complexes to establish the baseline sound isolation of the tested construction.

The measurements addressed impact and airborne transmission, giving ownership information relevant to the floor-ceiling assemblies. These were sound-isolation ratings rather than measurements of everyday ambient noise.

The client used the findings to inform which buildings could be considered for hard-surface flooring and which should retain carpeting. The program connected the material decision to measured building performance.

The result

The findings guided flooring decisions at the acquired properties and informed material choices in other portfolio buildings with similar construction.

This gave ownership a basis for renovation planning across the portfolio while preserving the distinction between properties tested directly and other buildings informed by that experience. The work helped the company evaluate flooring upgrades against the acoustic characteristics of its multifamily housing.

16 · Workplace Noise & Indoor Air Quality

Noise and indoor air quality assessment across software-company offices

A multi-facility assessment addressed call-center noise complaints and indoor air quality concerns. Testing identified elevated particulates at some facilities and elevated VOCs in enclosed private offices, informing filtration and material-selection recommendations.

The concerns

A major business-to-business software vendor retained OSAT to evaluate conditions across multiple facilities, with assessed spaces ranging from approximately 10,000 to 40,000 square feet.

Call-center employees reported having to speak too loudly during calls. In private offices, occupants reported allergy symptoms and other concerns about air quality. The assignment addressed these as separate workplace concerns: the acoustic conditions in the call centers and the measured air conditions throughout the facilities.

The assessment

OSAT evaluated call-center noise and conducted indoor air quality testing for particulates, carbon monoxide, oxygen, volatile organic compounds (VOCs), formaldehyde, temperature, and humidity.

The carbon monoxide measurements did not identify a safety concern, and oxygen levels were acceptable at all tested locations. Some facilities had elevated particulate levels, while enclosed private offices showed elevated VOC levels. These findings distinguished the locations and conditions needing attention from the parameters that were acceptable.

The recommendations

OSAT recommended improved filtration and further investigation with the client’s HVAC contractor. The advice focused on addressing the particulate findings and examining the building systems with the contractor responsible for their operation.

OSAT also recommended purchasing low-VOC furniture and carpet products to limit potential sources of indoor VOCs. This gave the client guidance for both building-system follow-up and future material purchases.

The outcome

The company received measured findings and recommendations for its facilities. The air quality results identified specific concerns without establishing that they caused the occupants’ reported symptoms.

The documented outcome was an assessment and a set of actions for the client to consider with its HVAC contractor and purchasing teams. Implementation and follow-up measurements have not been reported.

Discuss your project

What does your project need to establish?

Tell us about the facility, product, or measurement question. We can help define the appropriate testing scope.

Contact OSAT